Industrial Current

Distell Springs Phase II

Phase II upgrade of existing bottling facility

On completion of the recent 25, 000m² upgrade of Distell’s Springs bottling plant, NMC has been awarded an additional 1, 800m² section for upgrade. This includes the construction of; a new bottling line, offices, boiler room and mechanical room.

The project, which commenced in March 2012, is lead by De Villiers & Hulme and Stellenbosch based quantity surveyors, De Leeuw.

  • Location:  Springs
  • Client:  Distell (Pty) Ltd.
  • Contract Value:  R10 million
  • Project Duration:  4 months
  • Completion Date:  June 2012
  • Total area size:  1, 800m²